The current site is located in the village of Samoranovo.
The welded position is screed, which was cracked and with many destroyed places that had to be corrected in advance.
We built the edges and greased all the corners so that we could lay the liquid waterproofing on a solid and level base.
It was also necessary to adjust the base of the gutter. We built the end so that the water drained directly into the gutter and not along it.
After preparing the base, we primed with Hydroflex-Grund waterproofing primer.
We moved on to the waterproofing by first reinforcing the corners and damaged areas, after the primer is completely dry.
We applied two coats of liquid Hydroflex-Universal rubber to the entire base.
We finished the waterproofing with two layers in brown.